CBGM Installation - KCSL

Buyer: Kilnbridge Construction Services (UK)

Budget: GBP 250K

Published: 1/6/2026

Category: Aggregates

Description

Kilnbridge have secured the HS2 Old Oak Common Station Works Package WP13.01 for construction of the Urban Realm. Part of the scope requires the installation of Cement Bound Granular Material Subbase for the permanent road network. This is completed in phases/access date areas across the extent of the site. The Sub subcontract works includes the provision of all necessary People, Equipment, Plant and Materials for the installation and testing of CBGM. Works must comply with Series 800 and HS2 External Works Specification (provided upon engagement). Total CBGM subbase area is: 9400m2 Average CBGM thickness: 230mm Construction is to be carried out over a 2.5 year period commencing in Q3 2026 and completing in late Q2 2028. Multiple visits will be required over this period.

Source: official portal