🇩🇰Denmark·Buyer: FJERNVARME FYN AFFALDSENERGI A/S

Minor Overhaul of Steam Turbine Unit 13 (FFA13), 2025

Closed·10 Feb 2025·DKK 1,000,000

The scope of supply for this tender is a minor overhaul of the FFA13 steam turbine, gear and generator. The main target with the minor overhaul is to ensure that the unit is in a condition where it can be operated safely, reliably and efficiently until the next major overhaul. FFA13 is a waste-fired CHP plant commissioned in 1999 and having a capacity of 14 MW electricity and 42 MJ/s district heating. The turbine is running at 6950 RPM, and via a reduction gear the speed is reduced to 1500 RPM for the generator. The steam turbine is planned to be in operation until 2032 (as a minimum)

Published

10.02.2025

Open for bids

10.02.2025

Deadline

09.03.2025

© 2026 SIA «Vietne». All rights reserved.