The Contracting Entity intends to procure an Employer designed works Contractor for the construction of new electricity transmission infrastructure at the existing Belcamp 220 kV substation. It is envisaged that the scope of works to be procured under this Prequalification Questionnaire (PQQ) will be as outlined in section A.1.1 of the attached document. Economic Operators who wish to participate in this Prequalification Questionnaire process should submit a response as set out in section A.3 of the attached document. At the date of issuing this PQQ it is envisaged that the works will be constructed over a circa. 12–14 month period.

Publié

14.11.2024

Ouvert aux offres

14.11.2024

Date limite

16.12.2024